Repeater off-air. Stay tuned!
7/20/25 - More tower work was completed. Three more sections and guy wires are all that is left. Then work will start on the antenna and feed line, and grounding.
7/4/25 - Painting of the tower commenced a few days ago, and the first tower section was installed today. The final height will be 72ft.
6/21/25 - The first tower section was set, and 4400 lbs of concrete was poured for the foundation. The concrete will cure for 1.5-2 weeks before the remaining tower sections, 7/8 inch feed line, and antenna are installed.
A special thank you to Tyler Noll for his help pouring the concrete.
6/9/25 - The 40ft Rohn 25G tower has arrived from Illinois! The recent periods of rain have delayed site work for the foundation, but expected completion is within the next two weeks.
5/10/25 - Site work for the tower began today. Site work includes digging a 4x4x3 foundation, rebar framing, and setting a 5ft section of tower while filling with a few hundred pounds of concrete. The next steps are installing the remaining tower sections, antenna and feed line.
The tower being installed is a Rohn 25G. Final height to be determined.
4/28/25 - The first batch of BSCRA decals have arrived. These will be available in the near future.